Construction Report

9/24/2017
PROGRESS REPORT for our current building site: (Directions to the construction site are below.)

NOTE: The scheduled work hours for volunteers are 8:30AM to 4:00PM on Thursdays and Saturdays. Assume that you should bring a brown bag for your lunch on Thursday; lunch will be provided on Saturdays, unless otherwise noted.

Volunteers must personally sign-in at the work site each day in order to be covered by our insurance.  Please see our “How to Volunteer” (Volunteer Link) (HabitatOtsego.org)  for details on how to volunteer.

533 St Hwy 166 (Middlefield):

This past week we bored holes for the rough plumbing and wiring, and the rough wiring was completed for the bedrooms.  The electric panel donated by Green Mountain Electric Supply was installed.  A platform for the basement egress window was completed.  The basement sheetrock was completed.  And best of all, the siding was completed by the crew from St. Mary’s RC Church (Oneonta), with Tom Rowe guiding the crew.  

This coming week we will start the rough plumbing, continue work on the rough wiring, and start the roof.  Roof shingles and a shingle elevator are due on site Thursday morning.  

Respectfully submitted,
Mike Donahue (from information provided by Bruce Downie)
For the HFHOC Construction Committee

 Directions to 533 St Hwy 166, Middlefield:
From the center of Oneonta, take I-88 East (toward Albany) to exit 17. Turn left onto St Hwy 28 North and travel about 9 miles to the center of Milford.  At the traffic light in Milford, turn right onto St Hwy 166.  The build location is on the left about 2.1 miles from the light.

YOU’RE WELCOME TO STOP BY.

Leave Comment

Your email address will not be published. Required fields are marked *