PROGRESS REPORT for our current building site: (Directions to the construction site are below.)

NOTE: The scheduled work hours for volunteers are 8:30AM to 4:00PM on Thursdays and Saturdays. Assume that you should bring a brown bag for your lunch on Thursday; lunch will be provided on Saturdays, unless otherwise noted.

Volunteers must personally sign-in at the work site each day in order to be covered by our insurance.  Please see our “How to Volunteer” (Volunteer Link) (HabitatOtsego.org)  for details on how to volunteer.

533 St Hwy 166 (Middlefield):

This past week the underground electric service was re-worked and passed inspection, so  NYSEG turned the power on.  No more pulling the generator thorough the mud and starting it up!  The furnace installation is complete and the drywall is also complete.  Most of the perimeter insulation in the basement was installed.  We are making steady progress.

There will be NO work this coming week, while we take a much-deserved break for the Thanksgiving Holidays.  We hope everyone enjoys the time off with family and friends.

When we return on Thursday, Nov 30th, we will start taping and spackling.  We plan to get the LP gas installed between now and then.

Respectfully submitted,
Mike Donahue (from information provided by Bruce Downie)
For the HFHOC Construction Committee

 Directions to 533 St Hwy 166, Middlefield:
From the center of Oneonta, take I-88 East (toward Albany) to exit 17. Turn left onto St Hwy 28 North and travel about 9 miles to the center of Milford.  At the traffic light in Milford, turn right onto St Hwy 166.  The build location is on the left about 2.1 miles from the light.

YOU’RE WELCOME TO STOP BY.

Leave Comment

Your email address will not be published. Required fields are marked *